Production line 4 of the front spinning workshop of Dazheng Special Fiber No.2 has been put into operation

Column: Company News Release time: July 30, 2018 Browse:0
...

20187moon15After intense installation and debugging in the early stage, the front spinning of the second workshop of the company4The trial production of the spinning production line has been successful and officially put into use. At this point, our company's island fiber production capacity has reached12000The first phase of the project's production capacity construction has been completed in tons.

Workshop No. 24The production line was only used from project initiation to installation and commissioning completion4During this period, the equipment installation personnel put in arduous labor.

The production line 4 has been redesigned in terms of process flow, which differs from the production method123The No. 1 production line ensures the stability of product process quality, simplifies the front and rear spinning production processes, reduces production labor, and lays a solid foundation for the company to flexibly arrange production according to the product process requirements of different customers, further enhancing the flexibility of Dazheng Special Fiber's market development.

Consultation Hotline
Mr. Yu: 18766152658